Monday, April 11, 2011

Week Five

Monday- We sealed the hull of the boat with an epoxy seal and started working on the nose cone.

Tuesday- De-nibbed and made fair/smooth and glued up the nose cone.






Wednesday- Layed out 3 sheets of glass and applyed the peelply over the top and had to remake the nose cone for it was not up to the quality that we can achieve.

Chris and Jade came in on Thursday and put in a cove on the chine and installed the nose cone.

Week Four

Monday- We ALMOST got all the planking done! just no quite finished. And the deck building base was being made.

Tuesday- Sanded what we had layed down and at the end of the day we fitted in the last of the planks.




Wednesday- More sanding.... not very fun. Got up some more frames and filled some holes.

"not very fun"
unless you have one of
< Those

Week Three

Monday- We installed some more planks at the aft end to fill the last little gap that we had.


Tuesday- Sanded the area that we had already glue up and got that nice and smooth.









Wednesday- We were only able to get one more plank in between the several blank in the centre and the chine plank.